Monday, 4 May 2015

Week 14 - Plastering

Rain Rain Rain.

We lost about 4 days due to weather. But we still have made progress.

Once the scaff was up, the second floor was wrapped and the insulation and plaster was completed..
Insulation - they did a pretty good job. Everything was pack in nicely with no gaps. They did miss a spot where the air conditioning ducts run and under the bath tub.

Scaffolding was put up for works the second floor
Downstairs - plastering all completed.


Upstairs
We had some further delays to our second level bricks as the bricklayer decided to take another job on to complete that first..  lost about another week .

We have probably lost around 4 weeks of work due to weather and our brick layer woes... Can't wait to get to lock up!