The tiler has completed his work, most of the stone has arrived, they measured our ensuite stone incorrectly...

Painters have been booked in next week as the plasterer was finishing off today.

Unfortunately we are looking at delaying our handover to early August. Apparently there is a large trade shortage in SE Qld, plus plantation are building over 250 more homes than the previous year... Ah well...



Abey Undermount sink - I chose for the stone to over hang - this prevents water from being trapped and mould




Lunar white bench top 40mm

Laundry with subway tiling!



Powder Room


Lunar White bench top close up

Finger Mosaic - gaps will be filled with silicon

Main Bathroom sink - Polar - more stones visible compared to downstairs


Ensuite Niche

Still unstoned!