After a 2 week delay in finding a bricklayer we have brick off!
The moon dust bricks with off white mortar look better than I thought.
Pretty much the bottom half of the house has been bricked as of yesterday. Scaff is going up today for the rest of the house to be bricked.
Wednesday, 22 April 2015
Sunday, 12 April 2015
Week 8 - 10 - Electrical and Plumbing Rough-ins
All the plumbing and electrical was completed by week 9.
I went through our electrical plan to make sure all switchs, power points, downlights and data was completed exactly.
I picked up on a few downlights that wasnt quite in the right position, and I asked them to move our security equipment higher in our WIR so I can put a full height wardrobe in later.
I got my own electrician to run our CCTV cameras before the plaster went up.
Other items completed was our ducted airconditioning and all our plumbing done...
Our ground floor was wrapped, ready for the bricklayers to start just after easter, but unfortunately our bricklayer decided to quit! so we currently stuck without a bricklayer !!!! frustrating but part of the game!
Lots of water over easter - Not allowed WATER NEXT TO OUR SLAB. I brought this to the attention of our builder who got all this water sucked up! |